Bournemouth, Christchurch and Poole council has built an education centre from timber groynes reclaimed from the beach in an attempt to reduce the 2,000 tonnes of waste left behind on the sands each year. Thomas Lane looks at the project

Durley Chine hub from beach

Each year, some seven million people visit the golden sands of Bournemouth, an 11-mile beach stretching from Bournemouth in the middle to Sandbanks in the west and Christchurch to the east. Collectively, these visitors leave 2,000 tonnes of rubbish behind, which is removed and processed by Bournemouth, Christchurch and Poole Council at a cost of £1m.

Most of this rubbish is deposited in beachside waste bins, but sadly not all. The council has a dedicated site at Durley Chine beach to deal with up to 500 tonnes of litter left on the sands, which consumes half of the £1m budget. This facility has a dedicated team of staff to operate a fleet of tractors armed with special scoops to sift the rubbish out of the sand and pack it into containers ready for shipping out.

Durley Chine hub water refill area

The environmental hub is part of a strategy to reduce single-use plastics in the area. The council has installed water bottle refill stations along the beach

The cost and environmental impact of this waste prompted BCP council to commission a report called Turning the Tide, which recommended how to reduce the amount of single-use plastic on the beach. This includes providing free water bottle top-up stations along the beach and reducing single-use plastic use in beachside catering facilities run by the council.

The biggest element in this waste reduction strategy is a new environmental hub built next to the beachside waste site. Called the Durley Chine Environmental Hub, it integrates five functions and has been shortlisted in the net zero category at the Building Awards 2023, run by BD’s sister publication.

These include better quality welfare facilities for waste site staff, two meeting rooms for use by visiting schools and the community, a kiosk selling drinks and snacks, new toilets and an area for an exhibition to educate people about waste and recycling. Given its function, the building needed to be a sustainability exemplar, too.

“The specification for the project was to provide a very sustainable building, focusing on the environmental aspects, not only of the building, but also how it was going to be used in future,” explains Zoe James, BCP council’s project manager.

As the building would not generate enough revenue to cover its £2.4m construction cost, the council had to seek external funding. It drew up a rough “guide” scheme which included floor areas for each of the functions for a funding bid to the Coastal Community Fund. This was successful.

Armed with this rough guide, the council went to multi-disciplinary consultant WSP, which is on its consultants framework, and Footprint Architects to turn the guide scheme into a project that would meet the council’s aspirations.

Durley Chine hub centre

The exhibition space entrance is left open to encourage people inside. Reclaimed timber from a German naval base was used for the floor decking as greenheart wood is toxic

Peter Ward, the founder of Footprint Architects, explains that each of the five elements was carefully considered in terms of its function and the environmental strategy. “We split the building down into its functions and then created a bespoke environmental strategy for each one of those pods to enable us to reduce the heating requirements and reduce carbon,” he says.

The welfare facilities and meeting rooms are housed in a two-storey block on the east side of the scheme with the toilets and kiosk on the west side. The exhibition space is sandwiched in the middle and is open.

“An open space for the visitor centre is likely to be more appealing and bring people in than one with doors,” Ward says. These disparate elements are united by a green roof covering the two-storey block, the exhibition space and kiosk with the toilets left as a freestanding unit.

Ben Moss, director of building structures at WSP, says involvement right at the beginning of the project was a bonus as it enabled the team to thoroughly appraise the energy use and embodied carbon impacts of a range of options. “We even queried whether we needed foundations,” Moss says. “We went through the analysis and concluded that, in this location, foundations were a good idea.”

He says that BREEAM was not appropriate for this project, but building to Passivhaus standards would reduce energy use in the welfare and meeting room block. But Passivhaus was not extended to the toilets and kiosk because the extra insulation needed to meet the standard would increase the embodied carbon without reducing operational carbon. This is because the kiosk window is open all day and the toilet doors are constantly opening and closing.

Durley Chine hub toilets and kiosk

The walls of the toilets and kiosk are built from layers of concrete made from differently sized and coloured aggregates and sand to echo the seaside location. The concrete is made with a minimal quantity of cement

The toilet and kiosk walls are built from concrete. Moss says the original aspiration was to use rammed earth, but this was deemed unsuitable for the harsh beachside environment.

“What we wanted was a building that feels very contextual and weathered with its surroundings,” Ward says, adding that he wanted the kiosk and toilet walls to reflect the sand of the beach and strata of the cliffs. This has been achieved using several layers of concrete made from different sizes and colours of sand and aggregate.

The use of concrete sounds counter-intuitive in terms of embodied carbon, but Moss says the analysis shows otherwise. The single-storey walls carry relatively small loads so did not need any reinforcement.

The cement content of the mix was reduced by 30% because a strong concrete was not necessary for strength or reinforcement protection. Furthermore, 80% of the cement content has been replaced by GGBS. The wall is slightly thicker to compensate for the lack of reinforcement.

“We cross-checked against what the embodied carbon would have been if we had gone for a thin reinforced concrete wall and concluded that we had indeed saved some carbon,” Moss says.

Groynes on beach

Timber groynes help to protect the beach and shoreline from erosion. Made from durable tropical hardwood, the posts can go down to a depth of 7m

What is unique about this job is the extensive use of reclaimed timber. The building includes 45 tonnes of wood reclaimed from the groynes – shore protection structures – on the beach. There is a further seven tonnes of wood reclaimed from a naval yard in Germany.

The timber has been used for the secondary roof structure, brise soleil, cladding and the decking. Getting to this point has taken a lot of hard work and determination because reusing timber is much more involved than reusing steel, which is a more predictable and easily assessed material.

Reclaimed timber in yard

Structural engineer Ben Moss spotted reclaimed timber groynes stacked up in a yard by the beach when out on a run

Moss spotted a stockpile of suitable timber while out on a run. “I live locally and was out for a run one day and found this massive stockpile of timber in the Solent Beach carpark that the council had extracted from the groynes,” he says.

The groynes are replaced every 25-35 years and the council is also going through a process of realigning the groynes along the entire seafront as part of a 100-year project to provide more effective beach protection. The groynes are constructed from a combination of greenheart and ekki, which are both durable tropical hardwoods suitable for marine applications.

Each groyne consists of posts which go down up to 7m into the sand, and planks fixed between the posts. Some of the timber is reused for other projects but not all – Moss says there was plenty of leftover timber suitable for the environmental hub.

Once the flood and coastal risk management team, who are the custodians of the timber, had been persuaded to part with some of it, the timber had to be checked to see if it was indeed suitable for a building. “From the section size point of view, it looked suitable and it’s tropical hardwood, mostly greenheart, so we knew it was going to be pretty strong,” Moss says. “But then you have to start researching how you actually go about it. For example, how do you check that it really is greenheart?”

Moss brought Phil O’Leary, technical manager of Trada, which specialises in timber testing, certification and consultancy to assess the old groynes. “Phil gave us a bit of a conundrum because he said we couldn’t just say, because that was greenheart grade D70 20 years ago, it still is.

“It has to be regraded in the finished section size, so there is the risk of machining a whole load of timber to the right size and then finding out that it doesn’t meet the grading requirements and has to go in the skip.”

Building in a factor of safety by over-specifying the section size was considered then discounted because of the variability of the timber. “You can’t simply add a factor of safety and deliberately over-design because, if there’s a big knot or a crack, that might reduce the usefulness of the section from 100% to 0%,” Moss says. “With steel, generally we have a pretty good idea of provenance and it’s relatively easy to test.”

The answer was to do a quick initial grading. For example, knots have a bigger impact on the integrity of the timber than a hole of the same size. Moss adds that there is also a risk of weathered timber bending in one direction after it has been machined because of the difference in weathering on either side.

Timber with potential was machined to size. Machining was kept to a minimum to ensure the section sizes were as close as possible to the original. The design had to be tweaked to suit the available section sizes.

Durley Chine hub cafe area

Once funding becomes available, the external space between the kiosk and meeting room building is earmarked for an exhibition that will educate the public about waste and recycling. In the meantime, it is being used as a seating area for the kiosk

Finding someone to machine the timber also proved to be a challenge because of the size and density of the wood plus the risk of hidden nails damaging saws. A sawmill called East Bros Timber in Salisbury, which the council had used previously, was happy to take the job on.

Having got this far, the council wanted to know how long the timber would last once it was integrated into a building. “The answer is we don’t know, because there is no way of knowing how much of the inherent preservative qualities, the natural oils and so on have been leached out in over 20 years in the sea,” Moss says.

Unable to provide certainty, a decision was made to use new timber for the primary structure. “That’s why we’ve gone with new FSC-certified timbers for the key structural elements,” explains James. “Otherwise, we could have had issues when trying to get insurance.

“We were very comfortable with how the reclaimed timber has been used, but we did have to have those initial discussions about how to use the reclaimed timber safely.”

Durley Chine hub from west

The reclaimed timber groynes have been used for the cladding, brise soleil and secondary roof structure

The reclaimed timber has been used for areas where it can be easily replaced: the cladding, brise soleil, and areas where the wood will be protected from the weather such as the secondary roof structure. As greenheart is toxic and people are likely to walk into the visitor centre barefoot, the risk from splinters was deemed too high. So the reclaimed timber from Germany was used for the decking.

Moss says this project was only possible because of WSP’s early involvement in the design and the fact that the building was constructed by the council’s in-house contractor. “If we had had a traditional contractual arrangement, some of these things wouldn’t have happened because someone would have said this wasn’t in their scope or wasn’t what they priced for. We would have fallen foul of the ’it’s easier just to do it the way we always do it’ mindset,” he says.

The council’s contracting team’s positive mindset also helped. “The team were very enthusiastic about the building. It challenged but also really interested them as well, so they took on ownership,” James says. “The site manager, who is a chippy by background, was very into sorting out the detail – which was a real benefit.”

The finished structure will be net zero in operation as the roof-mounted PV panels provide enough power to heat, light and ventilate the building. The reclaimed timber and a general focus on reducing the carbon impact of all materials – such as newspaper-based insulation for the walls and recycled plastic splashbacks in the toilets – add up to an upfront embodied carbon figure of 172kg of carbon dioxide  per square metre including the exhibition space. This smashes the LETI 2030 upfront embodied carbon target of less than 300kgCO2/m2 for an education building, making it an A+ rating building for upfront carbon.

Durley Chine hub brise soleil

The reclaimed timber gives the building a rugged look that helps it to blend into its beachside surroundings

The building also looks great. The reclaimed timber cladding and layered concrete walls of the kiosk and toilets are very much of the beachside location, making it seem as if the building has always been there rather than recently finished.

The bonus of this approach is that the exterior should be virtually maintenance-free and durable, unlike other buildings on the beach front which suffer from saltwater-laden winds. Some relatively recent buildings have been demolished because saltwater has percolated through cracks in the walls and corroded the reinforcement.

Would the team use reclaimed timber for a construction project again? Moss offers a cautious yes, but says it is very project specific.

“We did have a nice alignment of those factors, which you won’t necessarily get on other projects,” he says. “You need this coincidence of circumstances where the project suits the supply of timber and the aesthetic too. We had a project where slightly ropey timber was what we wanted, so it all hangs together.”

He adds that regulation or cost savings would be needed to drive more widespread use of reclaimed timber. “If there is enough of a cost saving by reusing timber, then it will find its own way into the market – or, if regulation starts dictating it, then it will have to be done. But, compared to other building materials, timber is already a low-carbon material and therefore the incentive for people to use it isn’t that great.”

Durley Chine hub from east

With 7m people visiting Bournemouth beach each year, the environmental hub should attract plenty of interest

BCP council is in a good position to continue using reclaimed timber on future projects as it has a ready supply of high-quality durable wood, and a favourable supply chain arrangement. James thinks the reclaimed timber may have been cheaper than new as it did not cost anything, although the machining was expensive. The council is yet to do the sums.

James’s colleague, Andrew Brown, the council’s seafront operations manager, strikes a positive note. “The plan for this site is part of a much broader development plan for the seafront. So could reclaimed timber be used elsewhere? Yes.

“Some of those projects may come forward in the next few years subject to funding opportunities. And we may be in a similar situation; where timber is still being pulled out of the sea every year, it can be recycled and repurposed for those future projects.”

Brown adds that some reclaimed scaffolding boards were recently used on another kiosk further along the beach. Indeed all the signs are that the environmental hub has already proved to be a positive catalyst for change.

Project team

Client and project manager BCP Council

Architect Footprint Architects

MEP and structural engineer WSP

QS Peter Gunning and Partners

Employers agent Frazer Garner Associates

Passivhaus consultant Warm Consulting

Contractor BCP Council Construction Works Team

MEP specialist Spectrum Electrical Group